|
Find below the Flood defence
updates issued by the environmental agency
| Update
Number 18 July 2004
River Gaunless |
 |
|
River
Gaunless Flood Alleviation Scheme
The Works at Spring gardens are
progressing well. Over 90,000 cubic metres of clay has been formed and
compacted into the dam itself. The material was excavated from on site
borrow pits and have been completed just last week.
The next section of works will
include construction of the spillway, this can be seen in the photo as a
low spot over 150m long in the middle of the dam. Works are ongoing at
the bottom of the spillway placing concrete on the right of the
picture.
New access roads will be created
around the dam for use during maintenance and telemetry will be
installed to monitor water levels.
The photo shows the dam looking
West along the crest of the dam which is over 300m long and up to 15m
high.

| Spring 2004 Number 3 River Gaulness |
 |
|
|

Interserve Project Services Ltd, Site Office Spring Gardens Off the A68
Etherley Bank West Auckland Co. Durham DL14 0LG Tel: 01388 833569
Interserve Project Manager: Stewart Robertson
Environment Agency Ridings Area Office Phoenix House Global Avenue
Leeds, LS11 8PG Tel: 0113 213 4600
Environment Agency Project Manager: Don Robinson
 |
Major work on Spring Gardens Dam has progressed well during the
winter months.
The
concrete headwall structures at the inlet and outlet are
complete and twin 2.6 m diameter pipes have been installed.
Recycled material from the site was used to backfill the pipes.
Once this culvert work was competed, the river was diverted
into new river channels at the culvert entrance and exit. These
channels have been designed to redirect the flow of river water
through the pipes. A low flow channel has been created in the
river bed to allow the passage of migratory fish such as salmon
and sea trout when river levels are low. The new riverbanks have
been protected using recycled rock and hessian matting. This
will reduce erosion by preventing soil washing away before any
grass has grown. Along side the headwall of the dam an access
track has been created with gabions (rock filled baskets) acting
as a retaining wall. Four concrete trash poles (pictured) have
been built, to catch large debris such as tree branches and stop
it reaching the culvert and causing problems. Construction of
the dam itself has started on site, with the preparation of the
land and the installation of special equipment to monitor
settlement. Main building works are due to start shortly with
the extraction of materials from borrow pits on the site to be
used in the construction of the dam. It is anticipated that the
dam will be operational in October. Along with local defences,
the dam will help to protect 600 properties downstream that are
at risk from flooding |
|
West Auckland
Flood defence works at West Auckland are now almost
complete. 130m of sheet steel piled wall has been built and
clad in brick topped with coping stones. Riverbank erosion
protection has also been installed in this area.
South Church
Work in South Church has also progressed well and some areas
have been re-opened to the public up to St Chad’s Close.
Outstanding work consists of landscaping and fencing. These
works are dependant on the season and weather conditions,
but will be completed as soon as possible. Work is also
continuing at St Wilfred’s Walk and is almost finished.
Reinstatement work has begun and Interserve hope to have the
area re-opened to the public during the next few weeks.
Ramshaw
Works have been agreed with residents at Ramshaw Mill and
include floodwalls and embankments on the left bank and
local raising of ground levels on the opposite bank. Work
has also begun at Atherton Terrace and Gaunless Terrace.
Along Atherton Terrace the works will be very similar to
that at St Chad’s Close and St Wilfred’s Walk - a reinforced
concrete wall clad in brick and topped with coping stones.
(see right) |

 |
CONCERN LEADS TO DESIGN RETHINK
Flood Alleviation works to be carried out at
Gaunless Terrace have been redesigned to reduce their impact to the
public in the area.
The original plans would have seen the road closed for several weeks
whilst Interserve built 50 metres of steel sheet piled wall. But, due to
anticipated public concerns about the lengthy closure of the road, it
was back to the drawing board for scheme designers. This section of the
defences has now been redesigned and will consist of a ‘gabion’ (stone
filled baskets) alongside the river embankment. A reinforced concrete
wall will then be built behind the gabions to act as a flood defence for
the area. Interserve Project Manager, Stewart Robertson said: “This
section of the works was obviously going to result in considerable
disruption for local residents, which is something Interserve try to
avoid if at all possible. “By working with interested parties, the
Environment Agency and the Highways Agency we have come up with a
satisfactory alternative which minimises disruption and still provides
an excellent flood defence.”

South Church Defences completes

If you have any queries about the River Gaunless Flood Alleviation
Scheme and its impact on your area please call the Environment Agency
Supervisor on 01388 833569
Oakley Cross Beck Flood Alleviation Scheme
Following the
June 2000 floods the Environment Agency has been working on improving
the flood defences on the river Gaunless. The works include a flood
storage reservoir at Spring Gardens with local flood defences at West
Auckland and South Church. These are due to be completed by November
2004. With these defences in place 61 residential properties are still
at risk from flooding from the Oakley Cross Beck.
A study has been ongoing to look
at ways of reducing the risk of flooding to houses along the Oakley
Cross Beck. The study has now finished looking at several options and
following consultation with affected landowners, Local, County, District
and Parish Councils, we are designing the preferred option. Once built
the defences will reduce the risk of flooding to the 0.5% annual
exceedance probability, (1 in 200yr return period) the defences will
meet the same standard of defence as those on the river Gaunless.
All schemes are assessed
according to Defra procedures to ensure best use of public money. It is
for this reason that new defences will not extend as far down as Oakley
Green to protect the few properties at risk in this area. It is
anticipated that The Environment Agency will undertake some heavy
maintenance in this area later this year to improve the situation.
Following the detailed design
and the necessary approvals, Interserve Project Services Ltd, the
contractor working on the main Gaunless Flood Alleviation Scheme will
undertake the works.
Current Position
The detailed design of the
preferred option is being completed. Environmental improvements such as
tree and shrub planting are being incorporated to enhance the design.
Improvements are planned for West Auckland County School, the play area,
and within the grounds of Oakley Cross Beck School. It is hoped the
local primary school children will assist with the planting schemes. The
flood defence works will start in July and be complete by December 2004.
Local
Defences
Local defences are planned at the following locations:
·
Upstream of Staindrop road bridge on either
side of the Beck.
·
From the play area to downstream of Oakley
Cross Beck School.
·
Within the grounds of Oakley Cross Beck School
The new defences will consist of 300m of walls and 260m of earth
embankments. Access ramps over the defences will be constructed where
necessary. The locations of the defences are shown overleaf.
Floodwarning
A new flood warning service will
be available later this year for residents who are at risk from flooding
from the Oakley Cross Beck. Those at risk will have received letters by
now asking them to join the scheme.
Defences
upstream of Staindrop Road bridge

Defences alongside play area and
Oakley Cross Beck School

| Update
Number 1 October 2003
Oakley Beck |
 |
|
INTRODUCTION
Following the June 2000 floods
the Environment Agency has been working on improving the flood defences
on the river Gaunless. The works include a flood storage reservoir at
Spring Gardens with local flood defences at West Auckland and South
Church. With these defences in place properties are still at risk from
flooding from the Oakley Cross Beck. Earlier this year the Oakley Cross
beck was "enmained" to Acrum Lodge which gives the Environment Agency
powers to undertake channel maintenance and build new flood defences.
To reduce the risk of flooding
from the Oakley Cross beck, Halcrow Group have been appointed to
undertake a feasibility study, this will look at various options to
improve the flood defences along the beck. This study will consider the
technical viability, economics and environmental issues of the options.
Following this, the preferred option is chosen and outline designs
progressed.
All schemes are assessed
according to Defra procedures to ensure best use of public money.
Following detailed design and the necessary approvals a contractor is
appointed for construction of the works.
Current Position
The
environmental surveys, including habitat and species surveys, are
continuing. These surveys include studies of water vole, otter, bats,
badger, fish, birds and other flora and fauna. The completion of the
surveys and the ground investigation will allow the costs and design to
be accurately assessed.
We
are currently examining several options for flood defence.
Upstream Storage
This
option provides a flood storage reservoir that stores any floodwater
upstream of West Auckland. The reservoir would normally be empty and
would only fill if the river flow exceeds a certain amount, the
reservoir would then drain at a controlled rate over several days, with
this option flood defences would still be needed downstream.
·
Local Defences
This option provides flood defence embankments and
walls along the riverbank to help protect some of the areas that are
prone to flooding. With local defences there would be visible
embankments and walls along much of the riverbank.
·
Channel Improvements
This may include widening the channel and removing
obstructions to flow. This option would still require flood defences.
PUBLIC
DISPLAY
You
are invited to a public display on 21st October at St
Paulinus Church Hall, West Auckland between 1.30pm and 6.30pm. At the
display will be details of the various options under consideration on
which we welcome your feedback. There will also be information on the
main Gaunless Flood Alleviation Scheme and information on Flood
Awareness.
|